Specialty
Noise / Vibration
SECTOR
Energy / Power
TYPE
Permitting / Compliance
CLIENTELE
Private Sector
TIMESPAN
2001LOCATION
Madison, NY
Project Number:
2017Madison Wind Turbine Generating Station
SERVICE:
Noise Testing Protocol
DESCRIPTION:
Constructed in 2000, Madison Wind Farm was the first commercial wind farm in New York. Madison Wind Farm consists of 7 Vestas V66 1.65 MW turbines and has an installed capacity of 12 MW.
Tech Environmental recieved a contract from Vestas American Wind Technology to perform noise testing on the Madison Wind Turbine Generating Station in Madison, NY. As part of this effort, Tech prepared a testing protocol that included a field-monitoring program of up to five consecutive 8- to 12-hour days (starting on a Monday) for the purposes of establishing the sound power level of all seven wind turbines.